Project: Sterling GC Launch

Amendment to Member Test Plan

Dear RepoClear Participant

Members are advised that it has been necessary to make some minor alterations to the Member Test Approach document that you received on 31st July 2006. However, these alterations do not impact the intended go live date for the Sterling GC service on 23 October 2006.

Specifically, as a consequence of the CRESTCo Single Settlement Engine (SSE) release, the availability of a full end-to-end trialling environment has been postponed by one week from 2 October to 9 October, 2006. This delay will allow CRESTCo to ensure that the trialling environments reserved for the Repoclear Sterling GC activity are stable, processing efficiently and have all the necessary SSE changes applied. Both LCH.Clearnet and CRESTCo understand that whilst this may inconvenience members, we believe it is a prudent move which will guarantee the quality of the Sterling GC testing and subsequent launch.

Importantly, LCH.Clearnet and CRESTCo have endeavored to minimise these changes and therefore the resultant impact on members, whilst still meeting the original test objectives. The new revised Member Test Packs will be distributed on 19 September 2006.

For your information, 19 RepoClear participants have formally registered with LCH.Clearnet and will be part of the testing programme. 16 of them have expressed an intention to be part of the Sterling GC go live.

The new implementation and member testing timetable and approach will be as follows:

Summary of amended Sterling GC test plan

27 September 2006 - Scripted Connectivity Test with LCH.Clearnet and start of optional member testing

2 October 2006 - End of free format and scripted Member Connectivity Testing and start of CRESTCo Member Connectivity Testing

3 October 2006 - Start of Mandatory Scripted Member Test (not supported by CRESTCo)

6 October 2006 - Close of Mandatory Scripted Member Test

9 October 2006 - Inclusion of CRESTCo in Mandatory Scripted Member Test

17 October 2006 - End of Mandatory Scripted Member Test

18 October 2006 - Confirmation of live date notice sent by LCH.Clearnet

23 October 2006 - Intended go live date

30 October - Contingency live date

For further information on Sterling GC Implementation, contact: Nathalie Parquic, LCH.Clearnet Implementation Team, Tel: +44 207 426 7889, E-mail: nathalie.parquic@lchclearnet.com

For further general information, contact: Nick Maggs, Fixed Income Market Liaison, Tel: +44 207 426 7442, E-mail: nick.maggs@lchclearnet.com

Click to view a PDF version of this information